Work | CWU Development of RSPTN, IRC and WWTP University of Lampung |
Client | University of Lampung (UNILA) |
Contract No | 1484/UN26/HK.01/2024 |
Contract Time | Febuary 26, 2024 - August 29, 2025 |
Contract Value | IDR 198.865.665.859 |
Budget | LOAN ADB No. 4110-INO |
Project | Higher Education for Technology and Innovation (HETI) Project |
Location | Jalan Prof. Dr. Ir. Sumantri Brojonegoro No.1, Kota Bandar Lampung, Lampung 35141 |
Filter Data | ||
---|---|---|
Periode | ||
Date | January 19, 2025 - January 25, 2025 |
Contract Information |
Work Progress this ( Week 47 ) | Time Schedule up to ( Week 47 ) | ||||
---|---|---|---|---|---|---|
Plan Cumm. | Real Cumm. | Deviation | Based | Used | Reminder | |
INITIAL 0150/UN26/HETI.RSPTN/2024 March 8, 2023 - August 30, 2024 |
60.63% | 0.00% | 0.00% | 542 Days 78 Week |
324 Days 47 Week |
218 Days 31 Week |
CCO-01 xxxxxxxxxxxxxxxx March 8, 2023 - October 18, 2024 |
39.07% | 42.51% | 3.44% | 591 Days 85 Week |
324 Days 47 Week |
267 Days 38 Week |
Monitoring Work Progress ( Week 47 ) | ||||||||
---|---|---|---|---|---|---|---|---|
Description | Plan | Realization | Deviation | Remaining Progress from (100%) | ||||
until Last Sunday | This Week's Progress | until This Week | until Last Sunday | This Week's Progress | until This Week | |||
INITIAL | ||||||||
RSPTN | 58.15% | 2.21% | 60.63% | 0.00% | 0.00% | 0.00% | 0.00% | 68.74% |
IRC | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 31.26% |
WWTP | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
Total | 58.15% | 2.21% | 60.63% | 0.00% | 0.00% | 0.00% | 0.00% | 100.00% |
CCO-01 | ||||||||
RSPTN | 26.22% | 0.77% | 27.00% | 30.75% | 0.19% | 30.94% | 0.13% | 40.96% |
IRC | 11.91% | 0.16% | 12.07% | 11.27% | 0.30% | 11.57% | 3.31% | 16.43% |
WWTP | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
Total | 38.13% | 0.93% | 39.07% | 42.02% | 0.49% | 42.51% | 3.44% | 57.39% |
Description | Plan for Next (Week 48) | |
---|---|---|
Weekly Plan | Cumulative Plan | |
INITIAL | ||
RSPTN | 2.17% | 62.53% |
IRC | 0.00% | 0.00% |
WWTP | 0.00% | 0.00% |
Total | 2.17% | 62.53% |
CCO-01 | ||
RSPTN | 0.74% | 27.74% |
IRC | 0.16% | 12.24% |
WWTP | 0.00% | 0.00% |
Total | 0.90% | 39.98% |
No images available
Get in touch with us for more information about our programs and services.
Email: pmsc.unilaproject@gmail.com
Phone: +62 859-5404-1681
Address: Universitas Lampung, Jl. Sumantri Brojonegoro No.1, Bandar Lampung